Constructor Magazine

Feature

September/October 2009

Storm Surge: The Ongoing Evolution Of the Army Corps of Engineers

Post-Katrina rebuilding and the Mideast wars have pushed the Corps to tackle new delivery methods

By Angelle Bergeron

By June 30, 2009, Shaw Environmental & Infrastructure, Baton Rouge, La., was well on its way to delivering the $1.3-billion Lake Borgne Inner Harbor Navigation Canal storm-surge barrier, one of many large projects that will provide New Orleans with 100-year levels of protection by 2011.
By June 30, 2009, Shaw Environmental & Infrastructure, Baton Rouge, La., was well on its way to delivering the $1.3-billion Lake Borgne Inner Harbor Navigation Canal storm-surge barrier, one of many large projects that will provide New Orleans with 100-year levels of protection by 2011. (Photo By Angelle Bergeron/Constructor)

The U.S. Army Corps of Engineers has some new project-delivery tools in its arsenal, but obtaining them and learning to use them effectively sometimes has seemed like an uphill battle. Still, evolution of delivery methods in times of need, rather than revolution, seems to have been the best course.

The Corps’ tools must constantly change to fulfill its mission to “provide public engineering services in peace and war,” and the changes are “more evolutionary than revolutionary,” says Chris Jahrling, vice president of Turner Construction Group’s government practice in Washington, D.C.

One of the Corps’ struggles has been with design-build project delivery. Turner has been performing military construction work since 1917, and working with the Corps since the 1970s. Turner, a member of multiple AGC chapters, also has been doing design-build since the company’s inception and “as a bona fide delivery method in the market- place for the last 25 years,” Jahrling says.

But the Corps was limited to only a couple of design-build projects per year until the Federal Acquisition Regulations were changed in the mid-1990s, says Richmond Kendrick, deputy of program execution for the Corps’ Hurricane Protection Office in New Orleans.

Kendrick was the Corps’ civilian program manager for construction of the John J. Sparkman Center, headquarters for the U.S. Army Aviation and Missile Command and Logistics Support Activity in Huntsville, Ala. The 1992 groundbreaking on the project marked the first Army construction at the Redstone Arsenal since 1960. The Corps earmarked the project as design-build, and it was approved.

Storm Surge The Ongoing Evolution Of the Army Corps of Engineers Storm Surge The Ongoing Evolution Of the Army Corps of Engineers Storm Surge The Ongoing Evolution Of the Army Corps of Engineers

“Legislatively, we could only do two design-build projects per service per year,” Kendrick says. The performance-driven contract was such a success (built in 23 months for $88 per sq ft) that Kendrick began traveling the country giving Corps personnel training in design-build delivery.

Kendrick
KENDRICK

“I would say the Corps changes differently than the private sector,” Kendrick says. “There has always been adaptability, but when the Corps makes changes, perhaps it is a little more cautious. It is a big organization with a rich history and does not want to jump on just anything new.”

The Corps likes to think of itself as innovative, but the jury is still out on that issue, says Daniel Hitchings, former director of the Corps’ Task Force Hope and now program manager for Bioengineering-Arcadis LLC, Metairie, La., which performs design and construction management for Corps projects in south Louisiana.

Innovation is often stymied when weighing public funding and risk, Hitchings says. “Most of the projects they are doing, certainly on the civil-works side, have to do with public safety,” he adds. “How much risk do you want to take? If you do not have the confidence [a project] will work, the Corps will not do it.”

Hitchings
HITCHINGS

For projects like military barracks, the Corps has as little more wiggle room, Hitchings says. “You hear continually in technical circles that the Corps waits too long to adopt an idea that others have, but look what happens when something is not quite right,” he says, referring to levee failures in New Orleans and ongoing, intense public scrutiny of Corps contracts since then.“The Corps does stress innovative solutions, but you can be innovative without being risky,” Hitchings says. “It is a constant question of, How much innovation and risk is enough? The third thing is trying to keep costs under control.”

At times, the Corps leads private industry in innovation, says Michael B. Rogers, USACE account director for KBR Inc. in Arlington, Va., and former senior executive service member responsible for programs in the Corps’ Mississippi Valley Division. “The Corps changes, at least during my 25-year tenure, when the need arises to do something different,” Rogers says.

For example, in the mid- to late 1980s, the Mississippi Valley Division had a tremendous backlog of claims and contract changes and modifications. “Contractors were making a lot of money from claims for equitable adjustment,” Rogers says. So the Corps started partnering with the contracting community. “We really did not change our contracting methods, but we built a good relationship with the contracting community and opened up a dialogue that helped improve understanding and contracts,” Rogers adds.

Customer-Driven

Bertucci Contracting Co. LLC, Metairie, La., armored the bank line and water bottom on New Orleans’ London Avenue outfall canal as a subcontractor to a MATOC general.
Bertucci Contracting Co. LLC, Metairie, La., armored the bank line and water bottom on New Orleans’ London Avenue outfall canal as a subcontractor to a MATOC general. (Photo Courtesy of Bertucci Contracting Co.)

Customers’ demands and needs also drive change, Rogers says. For example, “the Air Force really had a problem with change orders and how fast things were being delivered,” he says. “They began to like design-build and drove the Corps to use it. In the end, the Corps did what it had to do to satisfy its customers’ desires.”

Mission and customers drive Corps changes, agrees Mike Rossi, chief operating officer of Vali Cooper International LLC’s Louisiana division in Madisonville, La., and a former commander of the Corps’ Kansas City District and the Washington, D.C., area’s $4.5-billion Base Realignment and Closure (BRAC) program. “Mission allows you to assume risk. A lot of time, the guys on the ground want to do it, but often it is the bureaucracy that pushes down innovation to buy down risk,” Rossi says.

Rossi is credited with introducing Early Contractor Involvement, a Corps variation of CM-at-risk, to the Kansas City District in 2003 and later to the Mississippi Valley Division and New Orleans. He says he felt the district was not getting enough bidders for work. So, “we went out to the big [contractors] in the Midwest and asked them why they were not bidding our work. They told us our risks were all wrong,” he says.

Rossi
ROSSI

Although the move seemed natural to Rossi, there is some internal pushback within the Corps to something new, he says. “They are worried about being exposed or setting precedent,” Rossi says. “Nobody will try a new contracting method without vetting it with their lawyers.”

The Corps has had a lot of growing pains since Hurricane Katrina revved up the pace of contracting and delivery for emergency repairs. When it became clear the program would be large (another $14.3 billion to bring the Greater New Orleans Hurricane and Storm Damage Risk Reduction System to 100-year levels by 2011) and done as quickly as possible, Hitchings says he began pulling in people like Kendrick and Rossi to introduce contracting methods necessary to make it all happen.

“We knew the normal Corps process was going to take too much time,” Hitchings says. “We knew that perhaps we were going to have to use cost-reimbursable contracts instead of firm-fixed price and maybe design-build instead of traditional.” Fully funded and with a deadline, the program in post-Katrina New Orleans demands innovation from everyone, Hitchings says.

Communication

Luckily, some key AGC members, like Tony Zelenka, New Orleans chairman for AGC’s Corps committee, had seen similar changes in Corps work with MILCON and BRAC. “With BRAC, they had to do about $62 billion in five years, and we have $14.3 billion in two years,” Zelenka says.

The Corps made additional changes to support the mission in New Orleans, including formally assigning other districts to specific tasks in New Orleans, says Karen Durham-Aguilera, director of Task Force Hope. “It is like the reach-back we have been doing in Iraq and Afghanistan. It is not just help; it means those districts are responsible for project management.” People often lose sight of the enormity of the mission in New Orleans, where the Corps’ pre-Katrina construction budget was $300 million a year, she says.

Durham-Aguilera
DURHAM-AGUILERA

“We realize how extremely complex and huge this work is in New Orleans,” says Freddie Rush, executive vice president of the Mississippi Valley AGC. But contractors need to better understand new contracting methods so they are not excluded from work, Rush says.

Zelenka says the Corps has made changes in New Orleans as it communicates with contractors. That evolution also was true of the Corps’ mission in Iraq. “Because of the $12-billion mission and conditions unknown, we started off with design-build in Iraq,” Durham-Aguilera says. “As time went on, we found you have to tailor the types of acquisition for the project. In Iraq, we transitioned away from design-build for technically complex work and used Multiple Award Task Order Contracts for brick-and-mortar projects.”

It is a challenge to demand change from contractors used to doing things a certain way, Rogers says. “But it is important to communicate with the Corps, and the Corps with you,” he says. “Nothing is going to stay stagnant.”

THE CORPS’ CONTRACTING TOOLBOX

“There are three basic ways to deliver a project: design-bid-build, design-build and construction management at risk,” says Mike Rossi, chief operating officer of Vali Cooper International LLC’s new Louisiana division and a former commander of the Kansas City District of the U.S. Army Corps of Engineers.

Early contractor involvement, or ECI, is simply the Corps’ variation on CM-at-risk, which Rossi started to use in the Kansas City District because the contracting community suggested it and he wanted to increase the district’s bidding pool. “The delivery method is still basically the Big Three,” Rossi says. “How you structure the payment and incentives and disincentives is different.”

ECI takes more work on the part of the owner and contractor as far as bookkeeping, but it offers an alternative in the contracting toolbox. “As the old saying goes, if all you’ve got is a hammer, then every problem is a nail,” Rossi says. “The Corps is now actually finding a way to use all three tools and the variations of them.”

The Hammer
Rossi refers to traditional design-bid-build as the hammer. “It is the best delivery method when you do not know what you want, and you have got a lot of time to build it,” he says. “You figure it out in design, and then you let the market price it for you.”

The Screwdriver
Design-build works when you know what you want and you have to go fast, Rossi says. “You put out a solicitation and say, ‘Give me what I want,’” he adds.

The problem with design-build is that if the owner thinks it knows what it wants at 35% of design, it puts a price on the project, but if it changes, there is a problem. “The key to design-build is that, when you put the request for proposals on the street, you are pretty solid in what you want and are willing to take what you get,” Rossi says.

The new tool: Early Contractor Involvement
ECI basically works when the other two do not, Rossi says. “ECI is when you do not know what you want and you do not have enough time.” Unlike design-build, ECI has a separate design contract. The owner is making the design decisions. “When you accept the design, you get a hard bid and move forward,” Rossi says.

Again, different methods apply to different types of projects. “There is no silver bullet out there,” Rossi says. “You can choose to do one method on the wrong kind of project or execute poorly, and you have bad results.”


AN UNPRECEDENTED CORPS EXPERIENCE

Hurricane Katrina changed the way the U.S. Army Corps of Engineers awards and delivers civil-works projects, and contractors who want to continue working with the Corps must adapt to change, says Tony Zelenka, president of Bertucci Contracting Corp., New Orleans, which is a member of Louisiana AGC Inc.

“What we are doing here is unprecedented anywhere in the world,” Zelenka says, referring to the $14.3-billion program to bring the Greater New Orleans Hurricane and Storm Damage Risk Reduction System to 100-year levels by 2011. “You can either fight it or jump right in and make it work for you,” he says. “The contractors who jump right in are going to make a lot of money.”

Bertucci’s business has tripled since Katrina, and that volume could push the small business ($33.5 million average revenue for the last three years) up a notch. “We will have trouble staying a small business, but that is not a problem,” Zelenka explains.

Bertucci was founded in 1875 and has been working with the Corps since the 1950s in New Orleans and along the Gulf Coast. Before Katrina, 99% of Corps work in the New Orleans District and Mississippi Valley Division was bid using invitation for bid (IFB).

Contractors were given a set of bid specs with a bid form, Zelenka says. Contractors completed the form, supplied the bid bond and sealed it all in an envelope. Bids were opened with all contractors present. The firm that had the proper form, bid bond and lowest price got the job, Zelenka says.

That worked fine in the historical, civil-works environment in which programs were incrementally funded and projects were slow to come to fruition, but after Katrina, time became critical because of the 2011 deadline, Zelenka says. To meet the pace of work and still get the best value, the Corps began issuing best-value requests for proposals, requiring contractors to propose how they will technically perform the job, as well as the time frame and price. Rather than the 30 days allotted for IFBs, contractors must supply their best-value RFP within two weeks.

“For contractors whose companies have been around 100 years, family-owned businesses, it is a significant shift in how they do business,” says Marco Giamberardino, senior director for AGC’s Federal and Heavy Construction Division. “If you are doing hard bid for 100 years and, all of a sudden, getting Early Contractor Involvement and design-build thrown at you, that is a major change,” he says.

With so many projects out for bid at the same time, many contractors have multiple proposals in play. “You do not know if you will get them all or none, which adds a great deal of uncertainty to your daily planning,” Zelenka says.

Because of minority participation goals on federal contracts, much of the work is being set aside and put into Multiple Award Task Order Contracts. “If you are not a minority, HUBZone or small disadvantaged business, you have to quote the contractors who are,” Zelenka says. “There are 11 contractors listed in the HUBZone MATOC.” That means the remaining contractors are excluded from bidding as a prime and are quoting projects as a sub to the MATOC contractors.

Most of the unrestricted competition jobs are big jobs now (more than $500 million), but only “a few contractors in the country can bid on these big jobs,” Zelenka says.

Both alternatives put longtime Corps contractors in the position of having to market to larger contractors. “Since we were always a Corps of Engineers contractor, we have no sales and marketing department,” Zelenka says. “We are selling services in a way we never had to before as government contractors. It is not worse or better; it is just different.”

Zelenka has an advantage as the New Orleans chairman of AGC of America’s Corps Committee. In that role, he already had been exposed to some contracting innovations through military construction and Base Realignment and Closure. “A lot of the issues we are seeing in New Orleans, the military did five years ago on BRAC,” he says.

AGC has been instrumental in helping members understand the “by-the-book procedures” of new contracting methods, as well as what it takes to remain competitive in the current market, Zelenka says. AGC’s partnership with the Corps at the district, division and national levels streamlined communications and helped to resolve problems.

AGC has a rich history of partnering with the Corps, but that relationship has grown stronger since Katrina, Giamberardino says. “I do think the Corps has a lot of pressure by Congress and other forces to deliver within a certain amount of time,” he adds. “We have always felt that an open dialogue and honest relationship is the best way to do business.”

Despite the challenges, the rewards of working in such a dynamic, fast-paced environment are invaluable, Zelenka says. “What we will all learn—both the Corps and the contracting community—in terms of professional and personal growth will be a tremendous experience.”